The relationship between the Last Planner System and collaborative planning practice in UK construction

Emmanuel Itodo Daniel, Emmanuel Itodo Daniel, Christine Pasquire, Christine Pasquire, Graham Dickens, Graham Dickens, Herman Glenn Ballard, Herman Glenn Ballard

    Research output: Contribution to journalArticlepeer-review

    151 Downloads (Pure)

    Abstract

    Purpose
    The purpose of this paper is to identify how the newly emerging UK practice of “collaborative planning” (CP) for construction project delivery aligns with the advocated principles of the global last planner system (LPS) of production planning and control.

    Design/methodology/approach
    A mixed, qualitative, exploratory approach was adopted for the study. This entailed qualitative data through three techniques, namely: semi-structured interviews, documents analysis, and structured observation. In total, 30 in-depth interviews were conducted over a 12 month period with lean construction consultants, clients, main contractors, and subcontractors drawn from the building, highways and infrastructure and rail sector. In all, 15 projects were visited where practices were observed.

    Findings
    The study reveals that the current practice of CP in the UK partially aligns with the LPS principles. Where practitioners have heard of the LPS they believe it to be the same practice as CP.

    Research limitations/implications
    This study is limited to 30 interviews, observation of 15 projects and document analysis. The aim of the study is not to generalise the findings, however, since the study examined top construction companies and practitioners in the UK and the findings were consistent across the sample, some conclusions could be made. The study is also limited to examining the construction phase only, future studies should incorporate the design phase.

    Practical implications
    A clear identification of the elements of current practice compared to the components of the LPS provides a contribution to the future practice of project production planning and management in the construction industry.

    Social implications
    The study highlights a continuing resistance to collaboration within the industry. This resistance is subtly embedded within implemented practices even though they are based on collaborative working for their success.

    Originality/value
    This is among the first studies in the UK that comprehensively examines and reports the application of LPS/CP practice in construction across the major construction sectors. Future studies could build on the findings from this work to develop an approach/methodology to improve the current practice.
    Original languageEnglish
    Pages (from-to)407-425
    Number of pages19
    JournalEngineering, Construction and Architectural Management
    Volume24
    Issue number3
    DOIs
    Publication statusPublished - 15 May 2017

    Fingerprint

    Dive into the research topics of 'The relationship between the Last Planner System and collaborative planning practice in UK construction'. Together they form a unique fingerprint.

    Cite this